Madison St. Project Updates

OVERVIEW OF MADISON ST. PROJECT

    The 2026 Madison St. Reconstruction Project (from 2nd Ave. E to 8th Ave. W) will begin mid-April and will be completed mid-October.   This     project will include water, sewer and storm upgrades, street reconstruction and sidewalk replacement.  

QUESTIONS ABOUT THE PROJECT

    Any questions about the project should be addressed to Public Works Director Matt Gilles at 715-672-8770 x 4 or to mgilles@durandwi.gov.  

PROJECT UPDATES 

Week of April 13 (updated 4/13/26)

    Work to be done: 

    Water main will be installed starting at 4th Ave. W to 1st Ave.

    Impact: 

    Street closures are to be expected.

 

 

 

Week of April 6 (updated 4/7/26):

    Work to be done:

    Trees along construction route will be removed.
    Blacktop will be removed on various blocks.
    Sidewalks will remain accessible.
    Some sanitary sewer replacement work may begin. 

    Impact:

    Watch for periodic street closures. 

Jan., 2026
Letter sent to all affected property owners re: the schedule, interruptions to services, etc.  (The letter can be found below).